Materials Management Plan

A materials management plan records how excavated material will be reused under the CL:AIRE code. The proposed use, supporting evidence and records must all stand up to scrutiny.

What a materials management plan is

A materials management plan, usually shortened to MMP, is the main document used to record proposed material reuse under the CL:AIRE Definition of Waste: Development Industry Code of Practice. It identifies excavated material, where it comes from, whether it is suitable for its intended use, the quantities involved and where it will be placed. The plan is supported by site information, risk assessments and records showing how the material is managed.

The code provides a voluntary framework for determining whether excavated materials used in land development and remediation are waste. Where its requirements are followed, suitable material can be reused without necessarily being subject to waste controls at the point of use. A plan alone does not establish that material is not waste. The proposed use must meet the relevant requirements, and the work must be carried out as recorded.

For a development involving excavation, this distinction affects how soil is assessed, stored, moved and documented. A site may have material suitable for reuse alongside other material that requires collection and disposal through an authorised waste route. We can assist with the waste management side, including collections, suitable containers and the relevant waste documentation.

Loader and conveyor building steaming heaps of shredded material on a yard.

When excavated material is waste, and when it is not

Waste status depends on whether the holder has discarded the material, taking account of the relevant legal tests and circumstances. The Environment Agency explains these considerations in its guidance on checking whether material is waste. Simply intending to reuse excavated soil does not establish that it is outside waste controls.

The CL:AIRE code provides a recognised framework for demonstrating appropriate reuse in land development and remediation. Relevant considerations include whether the material is suitable, whether its use is certain, whether the proposed use is defined and whether the quantity is appropriate for the works.

Material retained at its site of origin may have a different regulatory position from material transferred elsewhere. Direct transfer between sites and reuse following treatment also require consideration of the specific arrangements covered by the code. The origin, condition, intended destination and proposed treatment all matter when deciding which route is appropriate.

What the Environment Agency says about the code

The Environment Agency’s groundwater protection position statement J8 describes the code as a voluntary framework for determining waste status and maintaining an auditable record of material reuse. The Agency states that it supports the code and takes it into account when regulating development activities.

The published position is that materials managed in accordance with the code are considered unlikely to be waste when they are to be used for land development or remediation. The Agency also reserves the ability to return to individual regulatory decisions where audits identify improper use of the code that puts human health or the environment at risk.

The groundwater protection position statements publication is currently identified by the Environment Agency as under review. The code is not an environmental permit or a waste exemption, and a materials management plan is not itself regulatory approval. The appropriate arrangements depend on the material and the proposed works.

What the materials management plan needs to cover

The plan needs enough information to show that the proposed reuse is suitable, defined and supported by the relevant site assessments. For construction and remediation work, the information normally brings together the material characteristics, the design or remediation objectives and the controls that will apply during the works.

A useful materials management plan should address the following:

  • The site location, development activities and relevant planning context.
  • The source of the excavated material and the quantities involved.
  • The material characterisation, including available investigation and testing information.
  • The intended use and the requirements the material needs to satisfy.
  • The proposed destination and placement of the material within the works.
  • The storage arrangements and how different materials will remain identifiable.
  • The records required to demonstrate material movements and use.
  • The arrangements for material that cannot be used as originally proposed.
  • The responsibilities for managing, recording and verifying the work.

The plan is supported by an appropriate risk assessment, together with the relevant remediation strategy or design statement. These documents establish whether the material can be used for its intended purpose without unacceptable risks to human health or the environment.

The information must also reflect what happens on site. If the proposed use changes, the supporting documentation and records need to address the change rather than leaving the original plan as an inaccurate account of the work.

Worker in a helmet and high visibility vest holding a tablet beneath a steel and concrete structure.

The qualified person declaration

Under the CL:AIRE code, a qualified person reviews the proposed reuse arrangements and the supporting documents. The role includes checking whether the relevant requirements of the code have been addressed and whether the evidence supports the intended material use.

Where satisfied, the qualified person signs a declaration of compliance for submission through CL:AIRE. The declaration is submitted before use of the material for a site of origin project, or before dispatch under the applicable direct transfer and cluster arrangements. It is a notification under the code rather than approval of the plan by the regulator.

The Environment Agency may audit decisions made by qualified persons. Its published position emphasises professional integrity and a reliable record of the proposed material use. The qualified person declaration does not replace the responsibility to manage the material in accordance with the plan.

Material tracking, records and verification

A materials management plan needs to be supported by records of what actually happens during the works. These may include material quantities, excavation and placement locations, relevant testing, movement records and details of any departures from the original arrangements.

For example, if excavated soil is allocated to a particular area of a development, the records should allow that material to be traced to its intended use. Stockpiles should be identifiable, and the recorded quantities should be consistent with the material used in the works.

The code provides for a verification report demonstrating that the materials were managed and used as proposed. The Environment Agency’s land contamination risk management guidance also addresses verification evidence for remediation projects. Accurate records make it possible to establish which material was used, where it was placed and whether the relevant requirements were met.

Where material cannot be used as planned, the records should identify what happened to it and how it was managed. Material entering a waste route requires the relevant classification, transfer arrangements and documentation.

When waste management controls still apply

The CL:AIRE code does not remove waste controls from every excavation or remediation activity. The Environment Agency’s position statement J8 specifically excludes contaminated material moved off site for direct use elsewhere without treatment from the position described there. It also excludes the control of landspreading activities and the management of extractive waste under the relevant mining waste requirements.

Cluster projects may involve material being taken to a permitted treatment facility before subsequent reuse. The treatment facility’s waste permitting requirements remain relevant. Direct transfer arrangements and material retained at the site of origin must also be assessed against the applicable code requirements.

Where excavated material cannot be reused under the proposed arrangements, its waste status and the appropriate management route need to be established. This may involve waste classification, authorised treatment or disposal facilities, registered waste carriers and supporting records.

Our hazardous waste management information explains the handling of hazardous waste streams, while the waste transfer notes page covers documentation used for non-hazardous waste transfers. We can help arrange waste collections and the associated paperwork for material that needs to leave the site through a waste management route.

Materials management plans across the UK

The CL:AIRE code is used in England and Wales, with the relevant regulator’s published position informing its application. Natural Resources Wales supports the code and provides guidance on declarations for projects in Wales. It explains that excavated material can, in certain circumstances, be managed without being considered waste when the code is followed.

Scotland has its own regulatory position on the reuse of excavated material. The Scottish Environment Protection Agency has published guidance covering the reuse of greenfield soils in construction, with conditions concerning the type and condition of material. The position should not be assumed to cover contaminated soil.

Northern Ireland also operates under its own regulatory guidance. The Northern Ireland Environment Agency describes circumstances in which clean greenfield soil may not be regarded as waste. A greenfield soil declaration is required before movement under those arrangements, and the relevant paperwork must be retained for two years. The Agency does not issue formal consent in response to the declaration.

Projects involving several sites, contaminated ground or transfers between jurisdictions need to be assessed against the requirements applying to the particular material and locations involved.

Materials management plans and waste management plans

A materials management plan and a waste management plan serve different purposes. The materials management plan records the intended reuse of excavated material under the CL:AIRE code. A waste management plan deals with material managed as waste, including waste streams, storage, collections, destinations and transfer records.

Both may be relevant to the same development. Excavated soil suitable for reuse might be managed under a materials management plan, while surplus material, demolition debris and other waste require separate arrangements. The distinction is important when organising storage areas, collections and paperwork.

Our industrial site clearance service deals with the removal of unwanted materials, equipment and waste from industrial premises. The construction waste management page covers waste collections and handling associated with construction and demolition projects.

The waste hierarchy explains the general priority given to prevention, reuse and other waste management options. Where material must be managed as waste, we can help with the practical arrangements for containers, collections, recycling opportunities and the relevant transfer or consignment paperwork.

Free online tool

Waste Duty of Care Checker

Review common waste paperwork and collection questions relevant to your site.

Use the checker

Common questions

Frequently asked questions

What is a materials management plan?

It is the document at the centre of the CL:AIRE Definition of Waste: Development Industry Code of Practice. It records what excavated material a site holds, where it came from, that it is suitable for a defined use and how it will be used, so the material can be used in the works rather than handled as waste. It is a record, not a consent.

Does a materials management plan mean soil is not waste?

Not automatically. The Environment Agency says it supports the code and will take it into account when regulating development, and that materials dealt with in accordance with the code are considered unlikely to be waste at the point of use. That depends on the code actually being followed, including the material being suitable, with a certain and defined use.

Is the code a permit or an exemption?

No. Environment Agency guidance on treated soils presents three separate routes: registering a suitable waste exemption, applying for a permit, or using the code. The code does not involve approval of the materials management plan by the regulator, but a qualified person declaration must be submitted. The supporting records and verification evidence are also important.

What does the qualified person do?

The qualified person audits the development proposals for the material reuse. If satisfied that the reuse is in line with the code, they issue a declaration of compliance which is supplied via CL:AIRE to the Environment Agency before the material is used or dispatched. The Agency may carry out random audits of those decisions.

Can material be taken to another site under a plan?

Only within what the code and the regulator's position allow. The Environment Agency's position does not apply to contaminated materials that go off site for direct use elsewhere without treatment, which it still considers waste. Hub and cluster arrangements involve a hub site that holds an environmental permit for treating waste.

Does the code apply in Wales, Scotland and Northern Ireland?

Natural Resources Wales states that its regulatory guidelines support the code and it receives declarations for Welsh sites. Scotland and Northern Ireland work to their own published positions on excavated material instead, including a Northern Ireland greenfield soil declaration that must be submitted before the soil is moved.